PROGRESS MEETING MINUTES

 

DATE:  September 9, 2015                DATE OF MEETING: September 9, 2015

 

WIN: 20469.00  STP-2046(900)                                           TOWN: OXFORD

RICHFIELD BRIDGE OVER GREELEY BROOK GORE ROAD

 

ATTENDEES:

 

                        Eric D Rudolph                     MDOT Project Resident

                        Doug Gayne                           MDOT Product Research

                        Mitch Bois                              CPM Constructors

                        Dennis Laprell                       CPM Constructors

                        

 

SUMMARY:

 

 

  1. Review and Approval of Minutes of THE PRECONSTRUCTION  MEETING  

 

 

  1. Review of Work Progress Since LAST PROGRESS MEETING

           

RICHFIELD BRIDGE        –           BRIDGE REPLACEMNET           –           OXFORD

 

  • Mobilized
  • Set out Road closure signs 18 days before closing road
  • Erected the detour plan
  • De-energized the lines through the project
  • Set up MDOT Field Office
  • Cleared trees and bushes to the project limits
  • Installed erosion control measures
  • Removed pavement to the project limits
  • Installing riprap between STA 15+25 → 15+75 RT per the plans
  • Installed upstream sandbag cofferdam and downstream filtration cofferdam
  • Closed road on Thursday, August 20th
  • Removed the 2 culverts
  • Excavated and installed streambed liner riprap and riprap side slopes
  • Received reinforcing steel for Abutments, Approach Slabs, & Curbs
  • Mobilized pile driving equipment
  • Received piles
  • Performed a PDA for Abutment 2
  • Drove Abutment 2 piles to refusal
  • Placed concrete in the Abutment 2 Pile Jackets
  • Began building Abutment 2 forms and tying re-steel
  • Began driving piles at Abutment 1

 

 

Next meeting will be held on Wednesday   September 23, 2015     at 11:00 AM. At the MDOT Field Office located in front of the Greeley Brook Daycare (274 Gore Rd, Oxford, ME 04270). Please keep in mind that there is a detour. To get to the office you need to be on the Rt. 117 side of Gore Rd.

 

 

  1. Review of Work Planned Before Next Meeting

 

RICHFIELD BRIDGE        –           BRIDGE REPLACEMNET           –           OXFORD

 

  • Perform a PDA on Abutment 1
  • Drive piles at Abutment 1 to refusal
  • Continue to build forms and tie re-steel at abutment 2
  • Place concrete at Abutment 2
  • Build forms and tie reinforcing steel at Abutment 1
  • Place concrete at Abutment 1
  • Backfilling Abutment 2
  • Install French Drain at Abutment 2
  • Form and place approach slab at abutment 2

 

 

  1. Schedule of Work Status

 

The Contractor will submit an updated schedule.

 

  1. Review of Status of Submittals and Long Lead Items

 

Project Submittals/Working Drawings

 

Project Submittals/Working Drawings Status/Comments

 

Emergency Contacts SUBMITTED

 

Schedule of Work SUBMITTED AND APPROVED

 

Soil Erosion and Water Pollution Control Plan (SEWPCP) SUBMITTED AND APPROVED

06/23/2015

Spill Prevention and Countermeasure Control Plan (SPCCP) SUBMITTED AND APPROVED

06/23/2015

Traffic Control Plan SUBMITTED AND APPROVED

06/25/2015

Concrete QC Plan SUBMITTED AND APPROVED

08/26/2015

Concrete Mix Designs SUBMITTED AND APPROVED

08/26/2015

 

Contractor on site Safety Plan

 

SUBMITTED AND APPROVED

07/06/2015

ASC –Gravel SUBMITTED AND REJECTED WAITING FOR RESUBMITTAL

 

Granular Borrow  ( On Site ) SUBMITTED. WAITING FOR APPROVAL

 

 

WEAP Analysis for Pile Driving

SUBMITTED AND APPROVED

07/06/2015

Plain Rip Rap SUBMITTED AND VISUALLY  APPROVED

08/17/2015

Waste Area Permits Waiting for Submittal
Elastomeric Bearings SUBMITTED AND APPROVED

07/23/2015

Cofferdams Abutments  #  1  & #  2 INCLUDED IN EROSION CONTROL PLAN.
Paving QC Plan Waiting for Submittal

 

Erosion Control mix Waiting for Submittal

 

Loam Waiting for Submittal

 

Bridge Demolition Plan Waiting for Submittal

 

 

 

 

  1. Environmental ISSUES – Contractor has an Approved Erosion Control Plan.   

 

The Contractor has followed the erosion control plan and has added Additional Erosion Control Measures as needed.  The Contractor will keep a daily erosion control log.

 

 

  1. Traffic Issues – Contractor has an Approved Traffic Control Plan.

                                     

NONE.

 

 

  1. Field Observations – 

 

NONE.

                                              

 

  1. Contract Modifications and Invoice Issues.

 

                        The estimate has been generated and is current.

 

  • Contract Modifications to be done :

 

Need to generate Contract Modification the High Performance Waterproofing Membrane change to a Spray-on.

 

 

  1. request for INFORMATION; correspondence  –    

 

            NONE.

 

 

  1. PROBLEMS, CONFLICTS, AND PROBLEM RESOLUTIONS

No Outstanding/PENDING claims between the MDOT and The Contractor CPM Constructors 

 

  1. PROBLEMS CONFLICTS AND PROBLEM RESOLUTIONS FROM LAND OWNERS ON THE PROJECT.  

 

NONE.

 

  1. SUBCONTRACTOR ISSUES

 

NONE.

 

  1. ENGINEERING QUESTIONS AND ISSUES

 

There was a discussion on spray on membrane. The following questions were asked and will be answered:

  • Can traffic drive directly on the Spray-On Membrane?
  • If so, for how long?

 

 

  1. Review of Future Action Items – Priorities!!!

 

  • The Contractor has requested permission to work on Sundays within the road closure. There are 25 more days allowed on the road closure and CPM would like to utilize the 4 Sunday’s which fall between now and the re-opening.
  • The Contractor has submitted a request for time due ot the following: When laying out piles for Abutment 2 the contractor noticed that the overhead utility lines fall directly above the northern-most pile on both abutments. This caused them to lose progress starting Thursday, August 27th at 4:00 PM and continuing work Monday, August 31st once the utilities were all moved.

 

 

 

  1. PROJECT SAFETY ISSUES

                                                                                      

NONE.              

 

  1. UTILITIES  –            

 

See Section 15 – Review of Future action Items Subsection ii.

 

 

  1. CIVIL RIGHTS ISSUES –    

The Contractor has set up the Jobsite bulletin board with the required jobsite posters.

 

Any authorized persons who take exception to any statement in these minutes must notify the Resident in writing within seven days from receipt of the minutes, stating in detail the comment, correction or omission.  Otherwise, these minutes shall stand as written.

 

Prepared By:  ________________________

Eric D. Rudolph

Maine Department of Transportation

Gore Road Bridge Replacement

Eric.D.Rudolph@Maine.Gov

(207) 215-3724

 

 

 

cc:        Eric Shepherd                         MDOT Bridge Program

Devin Anderson                      MDOT Bridge Program

Rich Myers                              MDOT Bridge Program

Eric D Rudolph                       MDOT Bridge Program

Craig Hurd                              MDOT Bridge Program

Guy Whittington                     MDOT Contracts

Michael Clark                          MDOT Environmental

Joel Kittredge                         MDOT Bridge Program

Jerry Quirion                           MDOT Bridge Program

Mike Peterson                         MDOT Testing

Kevin Dill                               MDOT Testing

Roger Sproul                           MDOT  ROW

Gigi Ottmann-Deeves             MDOT EEO

Sherry Tompkins                     MDOT EEO

MDOT  Fabrication Engineer

Michael Redmond                  MDOT Bridge Program

Doug Gayne                            MDOT Product Evaluation Coordinator

Ted Talbot                               MDOT Office of Communications

Kyle Hall                                 Division office

Dana Hanks                            MDOT Traffic

Mitch Bois                              CPM Constructors

Peter Krakoff                          CPM Constructors

Dennis Laprell                         CPM Constructors

Stephen Estes                          P.Y. Estes

Bill Wolford                            Sealcoating

Michael Chammings               Town of Oxford

Cindy Richardson                   MDOT Bridge Program

Project file